Junior High Building Planning Update 9/18/17

The bid came in under budget for the early earthwork to begin this month at the Thomas Ewing site. Details for the athletic fields have been added to the site plans for Ewing. The design development (third planning phase) will be reviewed by the construction management firm later this month. The cost estimate for the General Sherman schematic design (second planning phase) is scheduled for later this month. Permitting and zoning processes with the city and county are on going.  