JH Construction Update 1/29/18

Planning progress meetings have been held this month to review and finalize plan details with engineers and architects for the following areas: Technology, Structure, Food Service, Plumbing, Electric, Architectural and Finishes, Casework and Furniture. The construction documents for the buildings are now 75% complete.  Traffic studies have been completed for both the General Sherman and Thomas Ewing sites and our civil engineer is in the process of incorporating the traffic study recommendations into the plans.  Earthwork will resume at the Ewing site as weather permits in March and will begin at the Sherman site in the spring.

Steve Wigton
Superintendent