JH Construction Update May 9, 2018

Foundation installation continues for the new Thomas Ewing Junior High in 4 of 5 sections of the building.  Foundations in the two story classroom section are almost complete.  The parking lot in the front of the building has been stoned and the athletic fields are being graded.  The electric and masonry contractors are in the process of moving onto the site in preparation to begin their work.  The site plans for General Sherman are being prepared to go through the city and county approval process.  Earthwork will begin after the plans are approved.

Steve Wigton
Superintendent