JH Construction Update 5/16/18

Foundation concrete blocks are being laid in the two story classroom section of the Thomas Ewing building.  Cement foundations continue to be poured in all sections of the building.  The grading of the track, football field and building perimeter are complete and topsoil has been respread on the site.  Installation of underground electric lines has begun and Accurate Plumbing is preparing to begin underground plumbing.  The General Sherman site is still in the approval process with the county and city.

Steve Wigton
Superintendent