JH Construction Update 6/13/18

Concrete block walls continue to be erected in all sections of the building with the two story classroom section nearing completion to the first floor.  The underground plumbing and electric in the two story classroom section is complete and the floor is being prepared for concrete pouring.  Underground plumbing installation is in progress now in the main entrance section of the building, which houses the media center, art rooms, offices, and 6th grade multipurpose lab.

Steve Wigton
Superintendent