JH Building Construction Update 7/11/18

At Thomas Ewing, the non-bearing internal concrete block walls are now complete in the two story classroom section of the building while structural steel continues to be erected.  In the main entrance section, a portion of the concrete floor has been poured and underground electric installed while concrete block internal walls are being installed.  Underground plumbing is complete in the single story classroom section while underground electric is being installed and the ground prepared for a concrete pour.  In the gymnasium section, underground plumbing installation is underway.

 

Earthwork has been approved to begin at the General Sherman site.  Equipment will begin to arrive on the site and earthwork will be getting underway over the next few weeks.

 

Steve Wigton
Superintendent