JH Construction Update 8/8/18

At Thomas Ewing, the stairs to the second floor classroom section are done, concrete block walls are being erected, and the second floor is being prepared for a concrete pour.  In addition storm drains, plumbing, electrical boxes and conduit are all being installed on the second floor. In the single story classroom section, concrete block walls and structural steel for the roof are being erected.  The floor in the gymnasium section is being prepared for a concrete pour.

Steve Wigton
Superintendent