JH Construction Update 9/19/18

At Thomas Ewing, concrete masonry blocks, storm drains, plumbing lines, electric boxes and conduit are being installed in the gymnasium and second floor classroom sections of the building.  Metal drywall studs are being installed in the main entrance section and both classroom sections.  Concrete masonry block and kitchen plumbing are being installed in the cafeteria section.  Internal concrete masonry block and ventilation ductwork are being installed in the first floor of the two story classroom section while metal roof joists are being installed in the gymnasium section.

 

The wet weather has limited the progress on at the General Sherman site.  The building pad continues to be prepared to pour foundations, weather permitting.  There will be an informational meeting about the General Sherman construction project for the community on October 2nd at Tarhe Trails Elementary School at 7:00 pm.  

 

Steve Wigton
Superintendent