At Thomas Ewing, brickwork is being installed on the highest areas of the building and restroom plumbing line installation continues.  Metal drywall framing continues both classroom sections of the building and in the main entrance section.  Electric boxes and conduit are being installed in the second floor classroom and gymnasium sections.  In the single story classroom section, ventilation ductwork and roofing are being installed.  In the gymnasium section, metal roof joists and mechanical room electric lines are being installed.  In the cafeteria section, roof joists and beams, underground kitchen plumbing, and electrical roughins are being installed.

 

At the General Sherman site, earthwork has resumed now that the weather has improved.  The building pad is roughed in and up to grade level.  The building pad will continue to be prepared with the addition of stones.

Steve Wigton
Superintendent