General Sherman JH Construction Update 1/8/2020

At General Sherman, the entire building plumbing rough in is complete and tested and DOAS units 1 and 2 are wired.  Chilled beam HVAC units are hung, data and network backbone wiring has been pulled, and chilled beam units are being hooked up the two story classroom section of the building.  On the second floor, lights are being installed and the ceiling grid is complete.  On the first floor, sprinkler drops and ceiling grids are being installed.  Chilled beam HVAC units are hung in the single story classroom section while data wires are being pulled.  In the main entrance section, the drywall is complete and first coat painted in the administration area, the metal entryway roof is in progress, and drywall is being installed in the media center.  The gymnasium ceiling has been painted and parking lot lights are being installed.

Steve Wigton
Superintendent





Back to School News      Print News Article